Sheet 02 — Turnkey Delivery
The Eight-Month Standard.
Groundbreak to energization in eight months. The complete facility, substation to white space. Done once at FRK-TX1, engineered to repeat.
Why modular wins
Built indoors, in parallel.
While foundations cure and the substation energizes on site, complete building sections are welded, fitted, and tested hundreds of miles away. The two schedules run at once.
What arrives is not a container. It is a finished slice of a Tier III-design facility, pre-commissioned as it ships.
Built indoors, tested twice
Every block leaves the line with its electrical rooms already energized once. Tested in the factory, commissioned after the crane.
FAT + ICT on every blockSitework never waits
Civil, substation, and utility scopes run alongside fabrication. The critical path is whichever finishes last, never the sum.
Fab ∥ site, month 0The same block, every time
Same block, same drawings, same crews, every campus. The risk falls out with repetition.
One design · every gridMonth by month
How eight months actually happened.
Release to fabrication
Land already powered, drawings already permitted. The factory cuts steel the week civil crews mobilize.
Foundations ∥ modules
Piers cure while the first hall reaches 80% fit-out indoors. Long-lead gear, bought at land close, arrives on schedule.
Set, stack, seal
Ninety-six module sets in six weeks. Commissioning starts in the first hall while the last one is still landing.
Energize
Backfeed, five-day IST, utility witness. 48 MW live, eight months after the first shovel.
Block Section 07 / 96
90% Complete at Shipment
What tenants get
The 48 MW block, in numbers.
| Block size | 48 MW critical IT, phased per campus |
| Rack density | 30–132 kW, direct liquid-to-chip ready day one |
| Design PUE | 1.15 annualized, closed-loop heat rejection |
| Water | 0 potable gallons for cooling at steady state |
| Resilience | Concurrently maintainable; Tier III design principles |
| Structure | Fully welded steel, engineered per-site for wind, seismic, snow |
| Delivery | 8-month standard from powered shell release |
Our delivery partner
Built with Brightray.
Brightray pioneered fully prefabricated data center construction. Hundreds of projects, and a record 90 MW campus delivered in eight months.
Ferrock holds priority capacity on their production lines and pairs it with what no contractor can supply: powered land, purchased gear, and capital that never waits on a close.